Ruby Hills Wind
Location: 10 km West of Walcha
Developer: Walcha Energy Projects by MirusWind and Energy Estate
140No. of Wind Turbines
800MWWind Turbine Capacity
Project Progress
- September 2020 Stage 1: Investigation
- Wind and Fauna Monitoring (continuous as the project progresses)
- 2020-2026 Stage 2: Design and Approval
- Government Submissions
- Government Approvals
- Environmental Studies
- Public Exhibitions
- Expected Mid of 2023 WE ARE HERE ⇒ Submission of Ruby Hills Wind Scoping Report to the NSW State Government
- Early Stage of 2026-2028 Stage 2
- Business Sessions
- Find Local Contractors
- Late Stage of 2026-2028 Stage 3: Construction
- Financing
- Prepare for Construction
Stage 3
- Construction
- Grid Connection
- Operation
Stage 1: Investigation
Wind and Fauna Monitoring (continuous as the project progresses)
September 2020Stage 2: Design and Approval
- Government Submissions
- Expected mid of 2023 WE ARE HERE Submission of Ruby Hills Wind Scoping Report to the NSW State Government
- Government Approvals
- Environmental Studies
- Public Exhibition
- Early Stage of 2026-2028 Business Sessions
- Find Local Contractors
Stage 3: Construction
- Financing
- Prepare for Construction
Stage 3
- Construction
- Grid Connection
- Operation
*Information available as of April 2, 2023
Note: The project timeline has not shown any decommissioning plan.